Dismantling
Ten-Hour DeWind D6 Dismantling
Location not specified
Dismantling of six DeWind D6 wind turbines. For one turbine, preparation took four hours and dismantling took a further six hours.
- Location
- Location not specified
- Service
- Dismantling
- Manufacturer
- DeWind
- Turbine model
- DeWind D6
- Turbines
- 6
Project Overview
Background & work performed
Ultra Wind Energy dismantled six DeWind D6 wind turbines. For one of the turbines, preparation took four hours and dismantling took a further six hours. The total duration for the full set of six turbines is not stated on the source page.
Scope of Work
Work stages
- 1
Dismantling of six DeWind D6 turbines
- 2
Preparation cycle of four hours for a single turbine (documented)
- 3
Dismantling of that same turbine in a further six hours (documented)
The Challenge
Dismantling several DeWind D6 turbines called for a disciplined preparation and dismantling routine so each unit could be taken down efficiently on the day of work.
Our Solution
Our team ran a structured preparation and dismantling cycle on each turbine — reflected in the documented single-turbine cycle of four hours of preparation followed by six hours of dismantling.
Media Gallery
On-site imagery
Project Enquiry
Request a Project Estimate
Share a few details and our team will reply with next steps.
Related projects

Decommissioning of Six AN Bonus Turbines
Decommissioning of six AN Bonus wind turbines in Büttel — four AN Bonus 600 and two AN Bonus 450 — and preparation of the site for newer wind-energy assets.
Read the Decommissioning of Six AN Bonus Turbines case study
Dismantling of Five Turbines in Feldheim
Dismantling of five wind turbines in Feldheim, Germany — four Enercon E66 and one BWU turbine — to prepare the location for future energy projects.
Read the Dismantling of Five Turbines in Feldheim case study
Dismantling of Two GE 1.5 Wind Turbines
Dismantling of two GE 1.5 wind turbines in Goslar, Germany.
Read the Dismantling of Two GE 1.5 Wind Turbines case study