Dismantling
Dismantling of Two GE 1.5 Wind Turbines
Goslar, Germany
Dismantling of two GE 1.5 wind turbines in Goslar, Germany.
- Location
- Goslar, Germany
- Service
- Dismantling
- Manufacturer
- GE
- Turbine model
- GE 1.5
- Turbines
- 2
Project Overview
Background & work performed
Dismantling of two GE 1.5 wind turbines in Goslar, Germany.
Scope of Work
Work stages
- 1
Dismantling planning
- 2
Turbine dismantling
- 3
Removal of dismantled equipment
Media Gallery
On-site imagery
Project Location
Goslar, Germany
Project Enquiry
Request a Project Estimate
Share a few details and our team will reply with next steps.
Related projects

Ten-Hour DeWind D6 Dismantling
Dismantling of six DeWind D6 wind turbines. For one turbine, preparation took four hours and dismantling took a further six hours.
Read the Ten-Hour DeWind D6 Dismantling case study
Decommissioning of Six AN Bonus Turbines
Decommissioning of six AN Bonus wind turbines in Büttel — four AN Bonus 600 and two AN Bonus 450 — and preparation of the site for newer wind-energy assets.
Read the Decommissioning of Six AN Bonus Turbines case study
Dismantling of Five Turbines in Feldheim
Dismantling of five wind turbines in Feldheim, Germany — four Enercon E66 and one BWU turbine — to prepare the location for future energy projects.
Read the Dismantling of Five Turbines in Feldheim case study